2003 - Chemical

The client was planning to change from a 8-hour to 12-hour shift pattern. The main driver for this was that they were having problems arranging cover for holidays, sickness etc. This had resulted in frequent working of double shifts (i.e. 16 hours). Andy made extensive use of fatigue research documented in HSE Contract Research Report 254/1999, and the working time directive and UK regulations. Communication was key element in this project and research about shift handover described in HSE offshore report OTO 96003 was used.

The client was planning to change from a 8-hour to 12-hour shift pattern. The main driver for this was that they were having problems arranging cover for holidays, sickness etc. This had resulted in frequent working of double shifts (i.e. 16 hours). Andy made extensive use of fatigue research documented in HSE Contract Research Report 254/1999, and the working time directive and UK regulations. Communication was key element in this project and research about shift handover described in HSE offshore report OTO 96003 was used.